The water tower was taken down last September. Photo by Sally Y. Hart

Lead that was found in the soil around the former water tower in Washington was recently safely removed and the cost for the work came in under budget.

The initial cost for the project was estimated at about $66,000. At Tuesday’s city council meeting, Mayor Sandra Johnson said the savings was $20,115.65. The work was done by DeLong Construction, Inc., of Washington.