In a matter of weeks, the new Washington Kirkwood Regional Facility will be finished. Tera Pickens, Director of the Washington Center, explains substantial work with contractors should be finished June 1st. After that, they will finish any equipment and furniture installations by mid-July. Summer classes end August 8th and the complete transition from the current building will be made in early to mid-August.

Last week, area superintendents and school officials toured the new Kirkwood Washington Regional Center. While school staff was there workers were on site installing carpet, working on drop ceilings and installing the exterior stone. For photos of the tour of the facility visit KCII’s Facebook page.