washington-county-logo-big

On the agenda at their Tuesday meeting, the Washington County Board of Supervisors discussed the Orchard Hill Remodeling Project. Supervisor Marcus Fedler gave an update on the project, “As you recall the overall project cost was about $180,000 higher than anticipated. We were able to cut $120,000 of that on this particular project, so in theory we are still about sixty away.” There has been no mention of when the renovations will be completed and when all of the county offices that will be moving to Orchard Hill will be relocating.